Construction World December 2015

A1

Civil Engineering Contractors

Kusile Combustion Waste Terrace

22

WBHO was awarded the Kusile Ash Dam contract in 2011, but due to permitting issues, construction only commenced in the third quarter of 2012. A major component of this contract is to line the proposed ash dam area. This opera- tion consists of a complex layer of different liner materials all aimed at preventing harmful substances from coming into contact with the environment. The sequen- tial set of operations involved in achieving this target is summarised in the following major operations:

1. Topsoil removal: vegetation is cleared and grubbed from the work area, topsoil is then removed and stockpiled for later reclamation works 2. Surface preparation: Exposed soil is ripped to 200 mm depth, moisturised, blended spread and compacted to achieve a smooth organic matter and stone free surface to receive the first bottom HDPE liner layer. 3. Bottom liner: The approved soil surface is then covered with a 2 mm double textured liner, welded, quality checked and handed over. 4. Bottom geotextile: The bottom HDPE liner is then covered and protected with an A8 Bidim layer. 5. Geo-cell: A 50 mm geo-cell matt is stapled together and stretched out over sloped areas, this is to prevent erosion in the leak detection area. 6. Washed river sand: a 100 mm washed river sand laver is spread over the Geo-cell and A8 bidim layer, which acts as a leak detection layer. 7. GCL: A Geosynthetic Clay Liner layer is then placed to cover the washed river sand layer. 8. Top liner: the GCL is covered with a 2 mm double textured liner, welded, tested, quality checked and handed over. 9. Top Geotextile: The top 2 mm HDPE liner is protected by an A8 Bidim layer.

10. Drainage layer: The liner and associated sandwich is them covered with a 300 mm drainage layer of G5 gravel. 11. Drainage pipes: A network of 50 mm perforated drainage pipes is then installed 200 mm deep in the drainage layer, cradled by washed sand and rapped in A4 Bidim. 12. Tie in: the perimeter of the HDPE liner ties into a leak detection channel connected to a concrete drain. This tie in consists of two rubber gaskets between the concrete and a stainless steel baton with holding down bolts every 250 mm. The first two contractual milestone dates on this contract was achieved and final comple- tion is expected within the allotted contract period in 2016.

Project information • Company entering: WBHO Construction

• Project start date: April 2012 • Project end date: April 2016 • Client: Eskom

• Project team: Kusile Executive Team • Main contractor: WBHO Construction • Principal agent: Eskom • Project manager: WBHO Construction • Consulting engineer: Worley Parsons • Design engineer: Knight Piésold Consulting Engineers • Project value: R1,1-billion

2 15 BEST PR O JECTS

CONSTRUCTION WORLD DECEMBER 2015

Made with