ROMPCO – Pipeline, Mozambique

was done using a degauss coil that induces an opposing current through the coil. This temporarily eliminates the magnetic field while completing the weld, but returns again slowly once the coil is removed. The construction of the new line was within 10 metres of the existing (opera- tional) gas pipeline, thus blasting was not the favoured option for the removal of rock. At first the trenching activities caused a number of delays. The contractor solved this problem by procuring two TESMEC trenchers to cut through the rocky sections. Eight new boreholes were drilled and sunk, each capable of delivering up to 10 000 cubes of water per hour. One of the bore- holes was sunk purposefully for donation to the surrounding community, Muabsa. This borehole was equipped with a hand pump and concrete base for water collection. The main design innovations came into play with the limited access of the Right of Way (30 m width). It had to be utilised not only for placing of the pipes (load and stringing), welding and coating activities but also for excavation, placing padding material (<12 mm) separate from excavated backfill material, placing concrete saddles in ROW and still have enough space to lower the pipes into the trenches. This had to be done without causing any harm to desig- nated wetland areas while still having access for local and construction vehicles in both directions at all times.

In October 2000, Sasol and the Government of Mozambique signed a Petroleum Production Agreement for the development of the Temane and Pande gas fields in Inhambane Province, Mozambique. This agreement was followed by the construction of an underground, 865 km long, high-pressure pipeline from the Temane Central Processing Facility in Mozambique to the Sasol Synfuels plant at Secunda, South Africa (Mozambique Secunda Pipeline). This current and existing gas pipeline is owned by the Republic of Mozambique Pipe- line Investments Company (ROMPCO) with Sasol, the South African and Mozambique

governments as the main stakeholders. The first section of this project was awarded to Group Five Civil Engineering in July 2013 and was successfully completed in November 2014. The Sasol, ROMPCO Loop Line 1 Project consisted of the construction of a 26 inch, 127 km long, pipeline running parallel to the existing MSP and located within the same 30 m wide servitude. The new pipeline was looped/tied in with the existing pipeline – increasing the carrying capacity of the pipeline. The overall project programme was 16 months. This included site establish- ment of a fully functional 400 man accom- modation camp, construction of the pipe- line, hydrostatic testing, commissioning and reinstatement. Saddles, or Set-On Weights, were used to secure the pipeline. For logistical purposes a concrete batch plant was established on site to cast the weights while a local laboratory was subcontracted to test and monitor the quality control of the concrete weights. The pipes utilised for the pipeline were ‘free issue’ and the clients responsibility (each 18 metre long). However some of the pipes delivered were magnetized as a result of the coating process during manufacture. This resulted inmany difficulties and dramat- ically increased the weld failure rate. It was necessary to demagnetise the pipes tempo- rarily in order to create a secure weld. This

36

Project information • Company entering: Group Five Civil Engineering

• Project start date: 05/07/2013 • Project end date: 11/04/2015 • Client: Sasol • Project team: Group Five Civil Engineering, WK Construction and WorleyParsons • Main contractor: Group Five Civil Engineering • Consulting engineer: WorleyParsons • Subcontractor: WK Construction • Project value: USD59-million