THE CONSTRUCTION OF SHONGWENI RESERVOIR 6Mℓ REINFORCED RESERVOR AND ANCILLARY WORKS

L ocated at the highest point in Ntshongweni within the eThekwini Municipality is the successfully completed Shongweni reinforced concrete water retaining structure. This reservoir plays a key role in supplying Ntshongweni, Ofudu, Salem, Clifton and Zwelibomvu reservoirs with sufficient portable water. The completion of the project has not only improved the level of service delivery for the Ntshongweni and neighbouring communities by providing water security, but has also left its mark through the realisation of significant social initiatives that have uplifted and developed the skills of local community members and targeted enterprise Contractors. The project has exceeded the contract goals in all areas of community-based activities such as Job Creation by providing accredited and on-the job practical training to local community members. This was realized via meticulous planning and social facilitation by eThekwini Municipality (Water & Sanitation), Naidu Consulting, and Afrostructures to display the art of Civil Engineering in rural KZN. Despite the complexities associated with the construction

of reinforced concrete structures and the social challenges faced following the KZN April 2022 floods, the main Contractor, with extensive co-operation from local labour and local contractors, was successful in overcoming challenges and achieving practical completion on 20 April 2023. Whilst strictly adhering to quality, safety and environmental constraints the project was completed prior to the initially planned Practical Completion date. 

PROJECT INFORMATION

• Client: JCM Solar Corporation Limited • End date: December 2021 • Main Contractor: HEJ Engineering

• Consulting Engineer: Zutari • Geotechnical: Geoconsult