Previous Page  22 / 56 Next Page
Information
Show Menu
Previous Page 22 / 56 Next Page
Page Background

20

CONSTRUCTION WORLD

FEBRUARY

2016

ith the main contract value of

USD90-million, the contract

had to be built in 24 months.

To meet the very tight

programme,

SS Construções opted to precast the curved

shaped concrete balustrades and cast them

into the edge of the in-situ coffer slabs.

The foundation design, consisting of

534 continuous flight auger piles, were

designed and installed by the Stefanutti

Stocks Geotechnical team, and

was completed in six weeks.

Design

The striking design of the two towers features

PROJECT PROFILE

the office tower with its curved shape as well

as a double conical shape in elevation. The

concrete balustrades interface neatly with the

curtain wall system while each floor is unique.

The apartment tower appears to mimic the

rippling shape of water with the clean lines

of the concrete structure enclosed with an

aluminium and glass façade system.

Construction innovation

technology

The two tower cores, consisting of five lift

shafts (each) were constructed with the use

of a hydraulic climbing shutter system, the

first of its kind to be used in Mozambique. The

slabs design employed the use of coffers and

a double boarding formwork design. Special

‘shoes’ were designed to position the precast

units onto so as maintain the line and level

during construction of the decks.

For the manufacture of the precast units,

SS Construções employed the services of SPE

(Specialised Precast Elements) in Gauteng.

Similarly, the four fire escape stairwells were

built with precast stairs and transported to

Maputo by road.

The use of the precast concrete elements

played a significant role in the success of

the project and provided the client with an

exceptionally high finish that will last for

many decades.

The 34 000 m

3

of concrete cast on the

project was largely batched on site with all

75 000 m

2

of slabs pumped from the batch

plant via a static pump.

Health and safety

The client’s project safety specification is

based on the South African construction regu-

lations. Suitable people to fulfill the roles of

all the required safety related appointments

and functions were trained in-house to meet

STRIKING TOWERS

in Maputo

By Tim Smith, contract manager.

The Horizon project in Maputo comprises a

19 storey apartment tower and a 15 storey

office tower that is positioned above a four

floor mixed use podium.