Construction World July 2016
AfriSam readymix has been used for the slabs, suspended slabs and columns.
Thompson says that a highlight of the supply contract has been ensuring timely delivery of quality concrete to site considering the very strict construction schedule. Aveng Grinaker-LTA Building and Enza Construction intend completing the bulk of the structure this year, giving them a long enough timeframe in which to handle the extensive and intricate finishings and fittings component of the project ahead of practical
In line with AfriSam’s policy, trucks are turned around within 45 minutes. The outlook for construction activity in INK areas of Durban remain strong, with the construction of Dr Pixley ka Isaka Seme Memorial Hospital a positive signal of more to come from both provincial and local govern- ment. And, AfriSam is in a very strategic position to play a meaningful role in many of these builds.
completion in the first week of October 2018. Up to 18 decks are prepared a day, with between five and seven completed in a week. The concrete supplied by AfriSam has been designed to cure over 28 days. Thompson says orders are placed at least a week in advance, with deliveries starting at 7:00 in the morning and ending by 17:00 when the construction shifts end.
Made with FlippingBook