Construction World October 2024

Two-stage tendering in SA’s construction sector is beneficial but NEEDS A COLLABORATIVE APPROACH Construction projects in South Africa are often concluded in a single stage - designs (usually incomplete) are used by the main contractor to provide tenders for constructing the project. Two-stage contracting is a growing trend, where engineers work in concert with the preferred contractor to finalise the design, typically from an early stage in the project life cycle, according to construction and mining law specialist MDA Attorneys. “T he combined effort upfront allows for quicker finalisation of the design and ultimately results in an improved

construction process. Instead of dictating to the contractor, who then must execute the project works, two-stage tendering allows for practical and realistic pre-qualification based on the contractor’s preferred method of working. Any changes can be ironed out early, reducing the likelihood of variations during project execution,” says Euan Massey, MDA Attorneys Director. Two-stage procurement in South Africa’s public sector The concept of two-stage procurement has been in place in South Africa for a while. An example is the two-envelope system used in public sector projects. This system involves an initial technical proposal without costs, aimed at establishing that tendering companies have the necessary skills and capacity to undertake the project. Once the bidders have been narrowed down to those with the skills and capacity, the second ‘envelope’ containing costs is considered, providing the ability to rule out contractors who are not proficient. Experienced contractors can make suggestions to improve designs to suit constructability, saving money and time, which is always attractive in construction projects. MDA Attorneys is seeing another benefit particular to South Africa in examples where contractors have developed relationships with local communities and subcontractors. Two stage procurement can enable the adjudication and negotiation of contracts based on the contractor’s track record in uplifting these local communities. Speed, accuracy and price certainty In single stage contracting, a main contractor bids on the work based on plans which have been drawn up by the client’s team. This traditional method gives clients a quick route to starting their project but all too often these designs are incomplete and require design finalisation. Any steps that can be taken to firm up the scope of work and allow for accurate pricing before the primary construction contract is awarded is an advantage to clients and they will pay a premium to have that certainty as soon as possible. Better scoping, lower risks On a two-stage contract, a contractor or group of contractors is brought on board to determine and cost works while carrying out preliminary activities (usually confined to the client’s design team). They do this while collaborating with the client and supply chain. The same contractor is not guaranteed to win the second stage, but it is usually in the best interests of both parties for it to continue with the contract. Two-stage contracts allow the contractor to properly

Euan Massey, MDA Attorneys Director.

understand the scope, raise questions regarding constructability and other risks such as ground conditions, and to price the work before it starts on site. Under two-stage contracts, clients will pay more up front before appointing a main contractor. However, this additional cost should be seen in context – without the early contractor involvement, tendering contractors will include contingency in their prices for the perceived risks in the project, resulting in additional costs to the client. Thus, advocates of two-stage contracts say it is in everyone’s interest to work closely together, citing the fundamental principle that planning ahead can usually save costs later on. This applies to construction more than most businesses because the costs of delay are so high. As with all relationships it will work far better if the parties work in a genuinely collaborative and trusting way. Narrow margins, greater risks Depending on the nature of the works, contractors on a single stage tender are unlikely to get more accurate pricing than around 10% of the final price. Overheads and profit will be priced at between 5-10%, making this a high-risk strategy. You’ll be happy if you get it right, but if you get it wrong, it’s a disaster. With two-stage contracting, clients run the risk that contractors are unrealistic in their initial pitch during the first stage to get into the second stage and then hike up their prices. 

35 CONSTRUCTION WORLD OCTOBER 2024

Made with FlippingBook - Share PDF online