Mechanical Technology March 2015

⎪ Power, energy and energy management ⎪

Zest Energy has applied its experience in electrical infrastructure, substations and power generation to install a 48 MW steam turbo generator set for Mondi in Richards Bay, with all the electrical integration scope carried out inhouse.” Several firsts for Mondi’s 48 MW cogen plant

T he Zest WEG Group, through subsidiary company Zest Energy and its technology providers has successfully completed a bench- mark steam turbo generator set contract at Mondi Richards Bay that showcases the Group’s value addition, innovation and customer focus. The original contract was awarded in May 2012 and partially handed over in December 2013, with final hand over in March 2014. This contract has been followed by a five year Long Term Service Agreement (LTSA), where Zest Energy will be responsible for the overall maintenance of the steam turbo generator set. Coenraad Vrey, managing director at Zest Energy, explains: “Essentially for the duration of the 24-month warranty period we have had to guarantee a mini- mum 98% availability, which has been linked to the execution of the LTSA. This means Zest Energy will co-ordinate the actual servicing under the supervision of our technology provider’s international service technicians. The agreement also includes the supply of all the necessary replacement parts and consumables.” The scope of work included the de- sign, manufacture and delivery as well as complete installation and commissioning of the steam turbo generator set and as- sociated equipment. Original equipment manufacturer (OEM) supervision services were also provided during installation and commissioning, with 24/7 on call sup- port for a period of four weeks following handover. The flagship project achieved a number of records: the largest ever steam turbine manufactured by technology provider TGM Turbinas. “Not only was this the first project to utilise a combina- tion of a TGM turbine with a WEG EM alternator, it was also a first reference for both equipment manufacturers in South Africa,” Vrey says. “Throughout the execution of this project, the Zest WEG Group has proved its ability to be involved in large scale

projects, not only from a standalone prod- uct supply perspective, but also from an integrated solutions point of view. This is an important achievement that will drive sustainable growth within the Group,” says Alastair Gerrard, general manager at Zest Energy. Zest Energy supplied the turbo genera- tor set equipment and took the overall lead on the package, which included steam technology from TGM Turbinas of Brazil and generator technology from WEG Electric Machinery of the United States. Local subcontractor TGS (Turbine Generator Services) undertook the me- chanical installation portion of the scope. Bosch Projects was appointed by Mondi as the official engineering, procurement and construction management (EPCM) contractor on the project. However, the steam turbo generator set was not only the system supplied by the Zest WEG Group to Mondi for this project. Zest WEG Group power division sup- plied two 132 kV/11 kV, 35/50 MVA ONAF power transformers; two 11 kV/550 V, 2.5 MVA transformers; one 11 kV/400 V, 1 MVA transformer; and an 11 kV, 300 A for 10s NEC/NER (neutral earthing compensator/resistor) for protection against earth faults. Zest WEG Group motors division supplied two 1.2 MW, two pole 11 kV compres- sor motors and two 560 kW, 12 pole 525 V booster pump motors, while Zest WEG Group subsidiary, EnI Electrical, completed the Mondi upgrade project on the electrical, instrumentation and control installation side. Mondi already had a 38 MW extrac- tion back pressure steam turbine and a 34.3 MW extraction condensing steam turbine and required a new 48 MW multi-extraction condensing steam turbine to take up the additional high pressure steam from the plant at full load. The power generated is used on site with the excess being exported to the national grid.

The beginning of 2013 saw the design and engineering phase of the project under full swing, with close scrutiny of the finer design details to ensure that no crucial element had been overlooked. Major long lead items such as the turbine casings and forged rotor shaft had al- ready been delivered to turbine manufac- turer TGM Turbinas, while WEG Electric Machinery clocked up similar progress. The Zest Energy project team was then faced with the formidable task of transporting the completely manufac- tured and assembled pieces of equipment to their final destination in Richards Bay, a task complicated by weather condi- tions and road transport restrictions. The process was finally completed in August 2013. Once on site, professional rigging sub-contractor Lovemore Brothers, under the supervision of TGS, was tasked with lifting and positioning the equipment in

18

Mechanical Technology — March 2015

Made with